A fast outage planning method focusing on circuit breakers near outage facilities

Chihaya Murakami, Aya Fujiwara, Shinichi Iwamoto

    Research output: Contribution to journalArticle

    1 Citation (Scopus)

    Abstract

    Japanese electric power utilities installed many electric power facilities for the increasing power demand in the high economic growth era. However these facilities have aged about 40 years and they should be replaced in the near future. The utilities will have to replace the facilities more than now at the same time because of the increase of the power facility replaces. Therefore the outage planning should take place more efficiently. However, to make the outage plan, it requires time and labor. Because the outage plan must determine 1 Outage schedule,2 Power system configuration during outage works and 3 System switching of the power system in order to conduct the outage works. To solve these problems, a fast outage planning method focusing on circuit breakers near the outage facilities is proposed in this paper. Finally, simulations are run using the IEEJ sub-transmission system model I to confirm the validity of the proposed method.

    Original languageEnglish
    Pages (from-to)746-752
    Number of pages7
    JournalIEEJ Transactions on Power and Energy
    Volume133
    Issue number10
    DOIs
    Publication statusPublished - 2013

    Fingerprint

    Electric circuit breakers
    Outages
    Planning
    Switching systems
    Personnel
    Economics

    Keywords

    • Outage planning
    • Sub-transmission system
    • System switching
    • Tabu search
    • Traveling salesman problem

    ASJC Scopus subject areas

    • Electrical and Electronic Engineering
    • Energy Engineering and Power Technology

    Cite this

    A fast outage planning method focusing on circuit breakers near outage facilities. / Murakami, Chihaya; Fujiwara, Aya; Iwamoto, Shinichi.

    In: IEEJ Transactions on Power and Energy, Vol. 133, No. 10, 2013, p. 746-752.

    Research output: Contribution to journalArticle

    Murakami, Chihaya ; Fujiwara, Aya ; Iwamoto, Shinichi. / A fast outage planning method focusing on circuit breakers near outage facilities. In: IEEJ Transactions on Power and Energy. 2013 ; Vol. 133, No. 10. pp. 746-752.
    @article{a7038b9896a24b3fb1565e8efd7bdf16,
    title = "A fast outage planning method focusing on circuit breakers near outage facilities",
    abstract = "Japanese electric power utilities installed many electric power facilities for the increasing power demand in the high economic growth era. However these facilities have aged about 40 years and they should be replaced in the near future. The utilities will have to replace the facilities more than now at the same time because of the increase of the power facility replaces. Therefore the outage planning should take place more efficiently. However, to make the outage plan, it requires time and labor. Because the outage plan must determine 1 Outage schedule,2 Power system configuration during outage works and 3 System switching of the power system in order to conduct the outage works. To solve these problems, a fast outage planning method focusing on circuit breakers near the outage facilities is proposed in this paper. Finally, simulations are run using the IEEJ sub-transmission system model I to confirm the validity of the proposed method.",
    keywords = "Outage planning, Sub-transmission system, System switching, Tabu search, Traveling salesman problem",
    author = "Chihaya Murakami and Aya Fujiwara and Shinichi Iwamoto",
    year = "2013",
    doi = "10.1541/ieejpes.133.746",
    language = "English",
    volume = "133",
    pages = "746--752",
    journal = "IEEJ Transactions on Power and Energy",
    issn = "0385-4213",
    publisher = "The Institute of Electrical Engineers of Japan",
    number = "10",

    }

    TY - JOUR

    T1 - A fast outage planning method focusing on circuit breakers near outage facilities

    AU - Murakami, Chihaya

    AU - Fujiwara, Aya

    AU - Iwamoto, Shinichi

    PY - 2013

    Y1 - 2013

    N2 - Japanese electric power utilities installed many electric power facilities for the increasing power demand in the high economic growth era. However these facilities have aged about 40 years and they should be replaced in the near future. The utilities will have to replace the facilities more than now at the same time because of the increase of the power facility replaces. Therefore the outage planning should take place more efficiently. However, to make the outage plan, it requires time and labor. Because the outage plan must determine 1 Outage schedule,2 Power system configuration during outage works and 3 System switching of the power system in order to conduct the outage works. To solve these problems, a fast outage planning method focusing on circuit breakers near the outage facilities is proposed in this paper. Finally, simulations are run using the IEEJ sub-transmission system model I to confirm the validity of the proposed method.

    AB - Japanese electric power utilities installed many electric power facilities for the increasing power demand in the high economic growth era. However these facilities have aged about 40 years and they should be replaced in the near future. The utilities will have to replace the facilities more than now at the same time because of the increase of the power facility replaces. Therefore the outage planning should take place more efficiently. However, to make the outage plan, it requires time and labor. Because the outage plan must determine 1 Outage schedule,2 Power system configuration during outage works and 3 System switching of the power system in order to conduct the outage works. To solve these problems, a fast outage planning method focusing on circuit breakers near the outage facilities is proposed in this paper. Finally, simulations are run using the IEEJ sub-transmission system model I to confirm the validity of the proposed method.

    KW - Outage planning

    KW - Sub-transmission system

    KW - System switching

    KW - Tabu search

    KW - Traveling salesman problem

    UR - http://www.scopus.com/inward/record.url?scp=84887087908&partnerID=8YFLogxK

    UR - http://www.scopus.com/inward/citedby.url?scp=84887087908&partnerID=8YFLogxK

    U2 - 10.1541/ieejpes.133.746

    DO - 10.1541/ieejpes.133.746

    M3 - Article

    AN - SCOPUS:84887087908

    VL - 133

    SP - 746

    EP - 752

    JO - IEEJ Transactions on Power and Energy

    JF - IEEJ Transactions on Power and Energy

    SN - 0385-4213

    IS - 10

    ER -