Abstract
In a response to economic growth, electric power utilities installed many electric power facilities to meet power demand. However, these facilities have aged and should be replaced in the near future. Moreover, the demand is said to constantly increase. Therefore, it is necessary to partially upgrade facilities. In this paper, we upgrade transformers with one of the financial engineering techniques. We also propose the method of upgrading transformers for improving reliabilities and economics.
Original language | English |
---|---|
Title of host publication | TENCON 2017 - 2017 IEEE Region 10 Conference |
Publisher | Institute of Electrical and Electronics Engineers Inc. |
Pages | 99-104 |
Number of pages | 6 |
Volume | 2017-December |
ISBN (Electronic) | 9781509011339 |
DOIs | |
Publication status | Published - 2017 Dec 19 |
Event | 2017 IEEE Region 10 Conference, TENCON 2017 - Penang, Malaysia Duration: 2017 Nov 5 → 2017 Nov 8 |
Other
Other | 2017 IEEE Region 10 Conference, TENCON 2017 |
---|---|
Country/Territory | Malaysia |
City | Penang |
Period | 17/11/5 → 17/11/8 |
Keywords
- Equipment Replacement
- Financial Engineering
- Optimal Portfolio Selection
- Power System
- Safety First Model
- System Planning
ASJC Scopus subject areas
- Computer Science Applications
- Electrical and Electronic Engineering