抄録
In this paper, we pay attention to the superior operating control function and instantaneous discharging characteristics of NAS battery systems, and propose a method for determining installation planning and operating control schemes of NAS battery systems for suppressing line overload phenomena. In the stage of planning, a target contingency is identified, and an optimal allocation and capacity of NAS battery systems and an amount of generation changes are determined for the contingency. In the stage of operation, the control strategy of NAS battery system is determined. Simulations are carried out for verifying the validity of the proposed method using the IEEJ 1 machine V system model and an example 2 machine 16 bus system model.