Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation

H. Kikukawa, I. Saito, M. Mori, H. Takahashi, Y. Honda, K. Murata, H. Katayama

    研究成果: Conference contribution

    抄録

    In this paper, concepts of visual management are designed to prevent the operational error of two adjacent similar switches, one typical problem of the process industry, in the chemical plant of the case company. The procedure of this study consists of three steps: Step 1) description of developed concepts, Step 2) design of standard for evaluating developed concepts and Step 3) evaluation of developed concepts. As the result of the evaluation of 7 developed concept, it is found that there are tread-off relationship between the usefulness of them and the easiness to install them. And then, concepts just before the operation are more important than concepts before the start of the operation. These findings are considered as one step to realize systematic development of a visual management tool.

    元の言語English
    ホスト出版物のタイトルCIE 2016: 46th International Conferences on Computers and Industrial Engineering
    出版者Computers and Industrial Engineering
    出版物ステータスPublished - 2016
    イベント46th International Conferences on Computers and Industrial Engineering, CIE 2016 - Tianjin, China
    継続期間: 2016 10 292016 10 31

    Other

    Other46th International Conferences on Computers and Industrial Engineering, CIE 2016
    China
    Tianjin
    期間16/10/2916/10/31

    Fingerprint

    Chemical plants
    Switches
    Industry

    ASJC Scopus subject areas

    • Computer Science(all)
    • Industrial and Manufacturing Engineering
    • Control and Systems Engineering
    • Electrical and Electronic Engineering
    • Safety, Risk, Reliability and Quality

    これを引用

    Kikukawa, H., Saito, I., Mori, M., Takahashi, H., Honda, Y., Murata, K., & Katayama, H. (2016). Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation. : CIE 2016: 46th International Conferences on Computers and Industrial Engineering Computers and Industrial Engineering.

    Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation. / Kikukawa, H.; Saito, I.; Mori, M.; Takahashi, H.; Honda, Y.; Murata, K.; Katayama, H.

    CIE 2016: 46th International Conferences on Computers and Industrial Engineering. Computers and Industrial Engineering, 2016.

    研究成果: Conference contribution

    Kikukawa, H, Saito, I, Mori, M, Takahashi, H, Honda, Y, Murata, K & Katayama, H 2016, Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation. : CIE 2016: 46th International Conferences on Computers and Industrial Engineering. Computers and Industrial Engineering, 46th International Conferences on Computers and Industrial Engineering, CIE 2016, Tianjin, China, 16/10/29.
    Kikukawa H, Saito I, Mori M, Takahashi H, Honda Y, Murata K その他. Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation. : CIE 2016: 46th International Conferences on Computers and Industrial Engineering. Computers and Industrial Engineering. 2016
    Kikukawa, H. ; Saito, I. ; Mori, M. ; Takahashi, H. ; Honda, Y. ; Murata, K. ; Katayama, H. / Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation. CIE 2016: 46th International Conferences on Computers and Industrial Engineering. Computers and Industrial Engineering, 2016.
    @inproceedings{9cbcb9a27c444ef782aacb6de465af21,
    title = "Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation",
    abstract = "In this paper, concepts of visual management are designed to prevent the operational error of two adjacent similar switches, one typical problem of the process industry, in the chemical plant of the case company. The procedure of this study consists of three steps: Step 1) description of developed concepts, Step 2) design of standard for evaluating developed concepts and Step 3) evaluation of developed concepts. As the result of the evaluation of 7 developed concept, it is found that there are tread-off relationship between the usefulness of them and the easiness to install them. And then, concepts just before the operation are more important than concepts before the start of the operation. These findings are considered as one step to realize systematic development of a visual management tool.",
    keywords = "Prevention system, Process industry, Visual management design",
    author = "H. Kikukawa and I. Saito and M. Mori and H. Takahashi and Y. Honda and K. Murata and H. Katayama",
    year = "2016",
    language = "English",
    booktitle = "CIE 2016: 46th International Conferences on Computers and Industrial Engineering",
    publisher = "Computers and Industrial Engineering",

    }

    TY - GEN

    T1 - Design of visual management tools for two adjacent similar switches in chemical plant and their evaluation

    AU - Kikukawa, H.

    AU - Saito, I.

    AU - Mori, M.

    AU - Takahashi, H.

    AU - Honda, Y.

    AU - Murata, K.

    AU - Katayama, H.

    PY - 2016

    Y1 - 2016

    N2 - In this paper, concepts of visual management are designed to prevent the operational error of two adjacent similar switches, one typical problem of the process industry, in the chemical plant of the case company. The procedure of this study consists of three steps: Step 1) description of developed concepts, Step 2) design of standard for evaluating developed concepts and Step 3) evaluation of developed concepts. As the result of the evaluation of 7 developed concept, it is found that there are tread-off relationship between the usefulness of them and the easiness to install them. And then, concepts just before the operation are more important than concepts before the start of the operation. These findings are considered as one step to realize systematic development of a visual management tool.

    AB - In this paper, concepts of visual management are designed to prevent the operational error of two adjacent similar switches, one typical problem of the process industry, in the chemical plant of the case company. The procedure of this study consists of three steps: Step 1) description of developed concepts, Step 2) design of standard for evaluating developed concepts and Step 3) evaluation of developed concepts. As the result of the evaluation of 7 developed concept, it is found that there are tread-off relationship between the usefulness of them and the easiness to install them. And then, concepts just before the operation are more important than concepts before the start of the operation. These findings are considered as one step to realize systematic development of a visual management tool.

    KW - Prevention system

    KW - Process industry

    KW - Visual management design

    UR - http://www.scopus.com/inward/record.url?scp=85013827070&partnerID=8YFLogxK

    UR - http://www.scopus.com/inward/citedby.url?scp=85013827070&partnerID=8YFLogxK

    M3 - Conference contribution

    AN - SCOPUS:85013827070

    BT - CIE 2016: 46th International Conferences on Computers and Industrial Engineering

    PB - Computers and Industrial Engineering

    ER -